Ceiling and kitchen floor materials removed before a whole-house remodel
Example project
- Home
- 1960s single-story house in La Habra, with textured ceilings throughout and sheet vinyl in the kitchen
- Original request
- Remodel the whole house, with new ceilings, a new kitchen floor and new lighting
- Testing
- A whole-house survey by a Cal/OSHA-certified asbestos consultant, about 12 samples
- Found
- Asbestos in the ceiling texture in every room and in the kitchen vinyl backing
- Clear
- The wall compound
- Area
- About 1,150 sq ft of ceiling and 220 sq ft of kitchen floor
- Timeline
- Notice no later than 10 working days ahead, then five working days
- Cost
- $16,800
In this example, a family is remodeling a 1960s house in La Habra. The city’s Building and Safety counter has an Asbestos Declaration for Demolition and Renovation, where the applicant states whether the job involves asbestos.